LER 96-014-01:on 961124,Class 1E Raychem cable splices were installed incorrectly.Caused by inadequate procedure.Splices were either confirmed to be acceptable by field insp or were replaced w/correctly installed splices. LER 96-014-01:on 961124,Class 1E Raychem cable splices were installed incorrectly.Caused by inadequate procedure.Splices were either confirmed to be acceptable by field insp or were replaced w/correctly installed splices.