LER 99-004-00:on 990126,plant was operating outside design basis.Caused because design for CR operator dose calculation did not consider single failure of CR ventilation sys. Revised CR operator dose calculation.With 990225 ltr. LER 99-004-00:on 990126,plant was operating outside design basis.Caused because design for CR operator dose calculation did not consider single failure of CR ventilation sys. Revised CR operator dose calculation.With 990225 ltr.