LER 99-003-00:on 990312,ESFA & entry into TS 3.0.3 occurred following partial loss of offsite power.Caused by failure of switchyard breaker.Licensee provided addl training on importance of conducting appropriate functional tests. LER 99-003-00:on 990312,ESFA & entry into TS 3.0.3 occurred following partial loss of offsite power.Caused by failure of switchyard breaker.Licensee provided addl training on importance of conducting appropriate functional tests.