LER 94-009-00:on 940918,determined that positive reactivity insertion occurred w/o operable boron injection flow path. Caused by EDG A being inoperable due to loose switch.Loose switch replaced.W/941007 ltr. LER 94-009-00:on 940918,determined that positive reactivity insertion occurred w/o operable boron injection flow path. Caused by EDG A being inoperable due to loose switch.Loose switch replaced.W/941007 ltr.