Notice of violation from insp on 940904-1015.Violations noted:licensee had not verified within last 18 months that EDG could energize swing HPSI pump 2P-89C through all time delay relay contacts during simulated LOOP. Notice of violation from insp on 940904-1015.Violations noted:licensee had not verified within last 18 months that EDG could energize swing HPSI pump 2P-89C through all time delay relay contacts during simulated LOOP.