Work schedule of the main inspection/restoration of the Kashiwazaki-Kariwa Nuclear Power Station in response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) (Appendix) Work schedule of the main inspection/restoration of the Kashiwazaki-Kariwa Nuclear Power Station in response to the Niigata-Chuetsu-Oki Earthquake (during 4 Weeks) (Appendix)