LER 96-007-00:on 950807,ventilation heat load calculations for EFW pump room did not reflect simultaneous operation. Caused by failure to recognize potential additional heat imposed.Interim ventilation measures added.W/960528 ltr. LER 96-007-00:on 950807,ventilation heat load calculations for EFW pump room did not reflect simultaneous operation. Caused by failure to recognize potential additional heat imposed.Interim ventilation measures added.W/960528 ltr.